Global Tech Company Case Study

Global Tech Company Case Study

Posted in Case Studies

Glenn Laga

THE RESELLER

Global Electronic Supplier and Integrator

THE CLIENT

Multi-Billion Dollar, Global Technology Company

THE SITUATION

The facility was a 100,000 sq/f data center with raised floors, over 900 server racks, telecom patch/panels, top run cable trays and associated wiring, metal security cages, seismic bracings and air handlers. The requirement was to catalog all components in the rack, remove and shred all hard drives on-site, remove all tech components from the building and then coordinate the recycling of equipment. The data center was to be left broom clean and free of all cables above the floor so the client could commence with the removal of the raised floors. The time frame allowed for this project was 22 days, meeting construction contractor’s time line.

THE RESPONSE

After coordination with the client on the time line and scope of work, Guardian performed site evaluation to assess physical inventory, building configuration, and shipping and storage resources. Next, Guardian worked in tandem with client to plan, manage and execute the extraction of material and components from the building. All secured material, assets and their components were safely recorded to match a master inventory list. Extraction and removal started with the physical disconnect of all wiring, manual unbolting of all the floor braces and bolts to cabinets, posts and bracings from the raised floor and from the drop down ceiling components (fiber trays and cable runners). The transportation of all material was coordinated by Guardian to be transported to a pre-determined recycler.

Guardian provided, in advance, all security and identification required of all on site personnel and met with the facility manager to be briefed on the client’s safety and security protocols.

THE RESULT

While working very closely with both the reseller and client, Guardian Data Destruction delivered a single-source solution from cataloging to data destruction, and completed the decommissioning of the entire data center slightly ahead of schedule and in full compliance with the SoW.

Contact Guardian Data Destruction Today
888.556.9473 (WIPE)

Ready to get started?

Get a quote > Discuss your challenge >

Data Center Lift & Shift project seamlessly executed, “Not even a phone call”

The Client APEX Global Systems is a full-service IT management provider for nursing homes across the US. Their mission is to create, develop and support …

Data Center Lift & Shift project seamlessly executed, “Not even a phone call” Keep Reading >

Keep Reading >

60,000 sq ft of buried, tangled (sometimes live) wire pulled, sorted and packed

The Client This Guardian Data Destruction channel partner is a leader in sustainable IT asset management and asset disposition (ITAD). Their client is a multinational …

60,000 sq ft of buried, tangled (sometimes live) wire pulled, sorted and packed Keep Reading >

Keep Reading >

Wrong site info jeopardizes decom deadline

The Client In an unusual partnership, two VAR and ITAD companies work together to supply IT hardware, IT services and end of life solutions including …

Wrong site info jeopardizes decom deadline Keep Reading >

Keep Reading >

Stay in the know

Get relevant information right in your inbox

We do not sell or share your information with anyone

Previous Next
Close
Test Caption
Test Description goes like this